The solution involved the following key components:
Check out our capability statement for a deeper dive into our highly competitive market offering.
Let’s do this together. Get in touch with our team.
The project encompassed site assembly of a 750tph Mobile Mining Unit at Tronox-Atlas-Campaspe Mine, OEM equipment handling, and thorough construction management.
The Carrapateena project included HDPE pipework construction with trunk lines, pump stations, bore field piping, mills piping, commissioning, hydrostatic testing, valve installation, and QA/QC control.